Good afternoon, Rohan

4 items wait for your review. 1 forwarded request needs a developer. 1 ticket is blocked.

23 Nov – 29 Nov
This week

Requests across the organisation

2with project managers
1waiting to be assigned
3with a developer
1done this month
0 daverage wait until assigned

Open requests by team

  • E-commerce2
  • Influencer marketing2
  • Sales1
  • Digital marketing1

People in the workspace

  • Admin1
  • Tech lead1
  • Project manager1
  • Developer7
  • Other team6
Manage people
Team efficiency
72%
Below target · target 85%
Ticket hours done
128 h
of 181.5 h at work so far221.1 h in the full week
Open tickets
16
Open bugs
4
50% bug points this week
Most ticket hours23 hArjun leads this week
Fastest bug fix5 hPnL date filter uses the wrong month boundary
On-time tickets100%15 of 15 approved by their date

Needs attention11

In progress
UG-074
Past its fix-by time by 0.6 working hAarav
Open
UG-076
Past its fix-by time by 20.6 working hVivaan
Fixed
UG-078
Fixed · ready to verifyArjun
Open
UG-079
Past its fix-by time by 35.6 working hSanya
Blocked
UG-007
Blocked: Waiting for the finance team to confirm the payout export columns.Vivaan
In progress
UG-004
Carried over from 25 NovAnanya
See all 11

Team efficiency by week

Since scores started
Average81%6 full weeks
Best week91%Week of 9 Nov
This week72%So far · hollow point
Weekly efficiency. Target 85%.
Week ofEfficiencyTicket hoursHours at work
12 Oct73%154231
19 Oct78%168231
26 Oct69%141231
2 Nov85%189231
9 Nov91%205231
16 Nov87%201231
23 Nov72%128181.5

Team this week7

DeveloperTicket hours doneOpen ticketsBug pointsEfficiencyOpen
Aarav Mehta3-week streak2 open tickets · 1 open bug
22 / 26.4 h so far83%
1 in progress1 in review
100%87%On target
Ananya Rao2-week streak2 open tickets · 1 open bug
20 / 26.4 h so far76%
1 to do1 in progress
100%81%Below target
Vivaan Shah3 open tickets · 1 open bug
14 / 23.1 h so far61%
2 to do1 blocked
0%1 scored48%Needs attention
Ishita Nair3-week streak2 open tickets · 0 open bugs
22 / 26.4 h so far83%
1 to do1 in review
100%1 scored87%On target
Arjun Patil3-week streak2 open tickets · 0 open bugs
23 / 26.4 h so far87%
1 to do1 in progress
50%1 scored80%Below target
Sanya Gupta1 open ticket · 1 open bug
18 / 26.4 h so far68%
1 in progress
100%75%Below target
Kabir Sethi4 open tickets · 0 open bugs
9 / 26.4 h so far34%
2 to do1 in progress1 in review
100%47%Needs attention

Project timelines

Work donePlanned timeExtensionToday
Project timelines
ProjectStartTargetFirst targetWork doneStatus
Creator marketplace12 Oct27 Nov13 Nov80%Behind plan
Inventory management5 Oct2 Dec2 Dec93%On track
Commerce5 Oct4 Dec27 Nov92%On track
Internal tools19 Oct1 Jan1 Jan92%On track